Updated information re Cove Blvd. Drainage Works.AS OF JUNE 8 2023
Council has advised that due to an eight week lead time currently required for the Contractor to obtain the required Concrete Pipes, the Works, whilst commencing later this month as previously advised, completion may now extend beyond August. This eight week lead time for supply of concrete pipe is the same everywhere. Residents will be kept informed if any further changes arise.”