Site Preparation and Electrical Outage Planned for Community Centre

By mpickles, 27 June, 2021

Preparations are complete for the installation of the new electrical pole at the Community Centre

MRM Powerlines have completed the drilling for the new pole and earthing at the Community Centre.

The area has been taped and residents are asked to keep off the area until the project is complete.

Electrical outage at the Community Centre has been confirmed for the 22 July when the pole and transformer will be installed, and connection to the building.

There will be the big drilling trucks on site that day so please keep the area free of cars.

Project funded by the NSW Office of Gambling Community Infrastructure.

Filed under